Heading towards completion of Energized Project areas in Dodoma

Print
Last Updated on Monday, 10 June 2013

Two substations at Mzakwe (11/33kV, 10MVA) and Mnadani (11/33kV, 15MVA) in Dodoma Region are to be energized on 16th and 20th June 2013 respectively.

Director of Energy, Eng. Isaac Chanji on 8th June 2013 made a site spot inspection to the ongoing commissioning works for substations at Mzakwe (11/33kV, 10MVA) and Mnadani (11/33kV, 15MVA) in Dodoma Region. The commissioning works for the two substations are scheduled to be energized on 16th and 20th June 2013 respectively.

Click here to download video clip taken at Mnadani substation when the Director was being briefed on the status of the commissioning work for the substation

Copyright © 2017 Millennium Challenge Account - Tanzania. All Rights Reserved.

This web site was made possible through a grant given by the people of the United States to Tanzania through the Millennium Challenge Corporation under the terms of a compact signed between the two countries. The information provided on this Web site is not official U.S. Government information and does not represent the views or positions of the U.S. Government or the Millennium Challenge Corporation.